RapidRide H Line construction update (Nov. 2021)

King County Metro, in partnership with the Seattle Department of Transportation (SDOT) and the City of Burien, is working to upgrade Metro Bus Route 120 — one of our 10 busiest routes — to the RapidRide H Line.

We will be sending email updates monthly to keep you informed on what to expect with construction activities over the coming weeks. We’ll also be reaching out to route neighbors, businesses, and local community organizations throughout construction to notify them when and where work will happen, as well as what impacts to expect.

Please feel free to share this information with your neighbors and encourage them to sign up for project email updates.

With construction getting underway throughout the project area, we invite you to take our construction survey to share comments, questions, and concerns, and to guide our outreach efforts.

Join us for our virtual construction office hours!

We are continuing to host biweekly virtual office hours from 4 p.m. to 5 p.m. every other Wednesday on Teams.

We hope you’ll join us to learn more about the project and to ask questions! These are informal events; we welcome you to come and go as you please.

Meetings will be held from 4 p.m. to 5 p.m. on the following dates:

How to join the meetings

What’s happening now

What to expect during construction

Construction on the RapidRide H Line project began in June 2021 and is expected to last through late 2022. Typical work hours are Monday through Friday, 7 a.m. to 3:30 p.m., with some nighttime and weekend work.

During construction, you can expect:

Crews are installing safety improvements and bus station upgrades along the route. Work has already started or will begin in the coming weeks at the following locations in Seattle, White Center, and Burien.

SEATTLE

Recently installed curb and sidewalk on SW Barton Street

26th Avenue SW between SW Barton Street and SW Roxbury Street

Note: People driving will not be able to access 26th Avenue SW from SW Cambridge Street

15th Avenue SW and SW Roxbury Street

26th Avenue SW and SW Roxbury Street

WHITE CENTER

Crews installing utilities along 16th Avenue SW

15th Avenue SW and SW 102nd Street

15th Avenue SW and SW 107th Street

16th Avenue SW and SW 112th Street

BURIEN

Preparing to install barrier curbs along Ambaum Boulevard SW

Ambaum Boulevard SW between SW 116th and SW 122nd Street

Ambaum Boulevard SW and SW 128th Street

SW 136th Street from Ambaum Boulevard SW to 8th Avenue SW

Questions during construction? Contact us!

We are committed to being a good neighbor. Thank you for your patience as we improve transit in your area. Keeping you informed and minimizing impacts are our top priorities. Throughout construction we will:

RapidRide H Line Outreach Team

Construction hotline: 206-257-3079

Email: rapidride@kingcounty.gov

Webpage: www.kingcounty.gov/metro/hlineinfo

Sign up for RapidRide H Line email or text alerts to stay up to date on construction schedule and impacts.