RapidRide H Line construction update (July 2022)

RapidRide H Line bus

What’s happening now

King County Metro, in partnership with the Seattle Department of Transportation (SDOT) and the City of Burien, is working to upgrade Metro Bus Route 120- one of our busiest routes to the RapidRide H Line.

We will be sending email updates monthly to keep you informed on what to expect near you. We’ll also be reaching out to route neighbors, businesses, and local community organizations throughout construction to notify them when and where work will happen, as well as what impacts to expect.

Please feel free to share this information with your neighbors and encourage them to sign up for project email updates.

Join us for our next virtual construction office hours

What to expect during construction

Construction on the RapidRide H Line project began in June 2021 and is expected to last through spring 2023. Typical work hours are Monday through Friday, 7 a.m. to 3:30 p.m., with some nighttime and weekend work.

During construction, you can expect:


(Map of active RapidRide H Line construction zones, including future RapidRide route and stations, road closures and detours, and temporary bus stop relocations)

Seattle


Crews pouring the bus zone foundation at 26th Avenue SW and SW Roxbury Street

26th Avenue SW and SW Cambridge Street

White Center

Crews setting crossbeam for inbound bus shelter

15th Avenue SW and SW Roxbury Street

15th Avenue SW and SW 102nd Street

15th Avenue SW and SW 107th Street

Ambaum Boulevard SW and SW 112th Street

Burien

Crews pouring the foundation of the bus zone foundation at 16th Ave SW and SW 116th St

16th Avenue SW and SW 112th Street

16th Avenue SW and SW 116th Street

Ambaum Boulevard SW from SW 116th Street to SW 122nd Street

Ambaum Boulevard SW and SW 128th Street

Ambaum Boulevard SW and SW 132nd Street

Ambaum Boulevard SW and SW 136th Street

Ambaum Boulevard SW and SW 138th Street

Ambaum Boulevard SW and SW 142nd Street

Ambaum Boulevard SW and SW 150th Street

SW 150th Street from Ambaum Boulevard SW and Burien Transit Center

Community happenings – NEW SECTION!

The South Delridge Farmers Market is taking place at HOPE Academy the second and fourth Saturdays of the month from 10am-2pm, through October. King County Metro will be at the Delridge Farmer’s Market Saturday, July 23. Stop by to learn about what’s new at Metro and to ask our team questions.

If you have community events to share in the area, let us know! Email us at rapidride@kingcounty.gov.

The Burien Farmers Market is open all year! Every Thursday from 10am-6pm (during May to October); and 10am-4pm (during November to April), taking place at the Burien Town Square Park. Stop by King County Metro as we will be there on July 21st, Aug. 4th and Aug. 18th.

If you have community events to share in the area, let us know! Email us at rapidride@kingcounty.gov.

RapidRide H Line to launch in March 2023

The original timeline of the RapidRide H Line project has been extended by several months due to unforeseen construction and materials delays. RapidRide H Line will now launch in March 2023 rather than fall 2022. Read more about the updated project timeline and construction progress on our blog.

Businesses are open during construction

With construction ongoing throughout the project area, Metro is reminding the public that businesses throughout the project area remain open. Visit our Metro Matters blog to learn more about Metro’s ongoing work in the Seattle, White Center and Burien communities.

Questions about construction? Contact us!

Thank you for your patience as we improve transit in your area. Keeping you informed and minimizing impacts are our top priorities. Throughout construction we will:

RapidRide H Line Outreach Team

Sign up for RapidRide H Line email or text alerts to stay up to date on construction schedule and impacts.