As early as Monday, October 10, 2016 a new interim park-and-ride lot (Lot B) will open across the street from the Northgate Transit Center at the southeast corner of NE 100th Street and First Avenue NE. The new interim lot is needed to replace stalls that will be unavailable after the Northgate Link light rail station construction begins later this fall.

Construction will occupy the west side of the Northgate Transit Center Park-and-Ride along First Avenue NE. The park-and-ride entrance on NE 100th Street will stay open at this time.

The capacity of the existing interim park-and-ride lot (Lot A) at the corner of NE 103rd Street and Fifth Ave NE will be reduced as Northgate Mall resumes exclusive use of some stalls.

As construction of the station progresses, we’ll keep you informed about additional changes to the park-and-ride.

For more information:

 

Map of Phase 1 Changes

  • 20160920-northgate-link-extension-parking-phase1