King County Metro, in partnership with the Seattle Department of Transportation (SDOT) and the City of Burien, is working to upgrade Metro Bus Route 120 — one of our 10 busiest routes — to the RapidRide H Line.
Following SDOT’s improvements to Delridge Way SW, Metro crews began construction of safety improvements throughout the project area in June 2021. Starting in fall 2022, RapidRide H Line will connect Burien, White Center, and West Seattle to downtown Seattle and South Lake Union. The RapidRide H Line will improve travel times, reliability, and connections to other buses and Sound Transit’s Link light rail.
What to expect during construction
Metro’s construction on the RapidRide H Line project began in June 2021 and is expected to last through fall 2022. Typical work hours are Monday through Friday, 7 a.m. to 3:30 p.m., with some nighttime and weekend work.
During construction, you can expect:
- Construction staging and parking impacts near the construction site,
- Some sidewalk, intersection, and lane closures,
- Detours for people walking, biking, and rolling,
- Noise, vibrations, and dust in the project area,
- Temporary parking restrictions,
- Periodic lane and driveway closures,
- Large machinery and truck activity,
- Flaggers to direct traffic around work areas,
- And temporary bus detours and bus stop relocations for Route 120.
What’s happening now
Crews are continuing construction of safety improvements and bus station upgrades along the route. Work has already started or will begin in the coming weeks at the following locations in West Seattle, White Center, and Burien:
SW Barton Street (SW Barton Street and 25th Avenue SW intersection, and the crossing between 26th Avenue SW and 29th Avenue SW)
- Sidewalk and curb ramp installation at the northeast corner of SW Barton Street and 25th Avenue SW.
- Demolition and sidewalk and curb installation at the northwest corner of SW Barton Street and 25th Avenue SW.
- Northbound and westbound station upgrades at SW Barton Street and 26th Avenue SW:
- Electrical work
- Foundation and sidewalk installation
26th Avenue SW (SW Barton Street to SW Roxbury Street)
- Demolition of existing pavement in the northbound lanes.
- Signal installation at the 26th Avenue SW and SW Barton Street intersection and 26th Avenue SW and SW Roxbury Street intersection.
- The northbound lanes of 26th Avenue SW between SW Barton Street and SW Roxbury Street will be closed to traffic.
- People driving will not be able to access 26th Avenue SW from SW Cambridge Street.
- The northbound bus stop at 26th Avenue SW and SW Barton Street will be temporarily relocated to SW Barton Street, within a block east of the intersection.
Intersection at SW Roxbury Street and 15th Avenue SW (southwest, southeast, and northeast corners)
- Storm, sewer, and utilities work
- Sidewalk and curb ramp installation
- Curb and gutter installation
- Traffic signal modifications
- Northbound and southbound station upgrades at SW Roxbury Street and 15th Avenue SW:
- Electrical work
- Sidewalk and curb installation
- Safety railing installation
Ambaum Boulevard SW (SW 116th Street to SW 122nd Street)
- Irrigation
- Curb installation
- Electrical installation
- Southbound station upgrades at Ambaum Boulevard SW and SW 122nd Street:
- Demolition
- Retaining wall replacement
SW 136th Street (Ambaum Boulevard SW to 8th Avenue SW)
- Demolition of sidewalk
- Electrical installation
- Storm drainage installation
- Sidewalk and curb installation
Questions during construction? Contact us!
We are committed to being a good neighbor and thank you for your patience as we improve transit in your area. Keeping you informed and minimizing impacts are our top priorities. Throughout construction we will:
- Be available for questions.
- Provide advance notice about construction through email updates, handing out flyers, and other promotions.
- Maintain access to businesses and residences.
RapidRide H Line Outreach Team
Construction hotline: 206-257-3079
Email: rapidride@kingcounty.gov
Webpage: www.kingcounty.gov/metro/HLineInfo
Sign up for RapidRide H Line email or text alerts to stay up to date on construction schedule and impacts.