King County Metro, in partnership with the Seattle Department of Transportation (SDOT) and the City of Burien, is working to upgrade Metro Bus Route 120 — one of our 10 busiest routes — to the RapidRide H Line.

We will be sending email updates monthly to keep you informed on what to expect with construction activities over the coming weeks. We’ll also be reaching out to route neighbors, businesses, and local community organizations throughout construction to notify them when and where work will happen, as well as what impacts to expect.

Please feel free to share this information with your neighbors and encourage them to sign up for project email updates.

What’s happening now? What to expect during construction

Construction on the RapidRide H Line project began in June 2021 and is expected to last through late 2022. Typical work hours are Monday through Friday, 7 a.m. to 3:30 p.m., with some nighttime and weekend work.

During construction, you can expect:

  • Noise, vibrations, and dust in the project area
  • Temporary parking restrictions
  • Periodic lane and driveway closures
  • Large machinery and truck activity
  • Construction staging and parking impacts near the construction site
  • Some sidewalk, intersection, and lane closures
  • Detours for people walking, biking, and rolling
  • Temporary bus detours and bus stop relocations for Route 120 and other area transit and bus routes.
  • Flaggers to direct traffic around work areas

map depicting future RapidRide station locations and active construction zones along the route 120 corridor.. Closure details are outlined in the text of this blogpost.

Crews are installing safety improvements and bus station upgrades along the route. Work has already started or will begin in the coming weeks at the following locations in Seattle, White Center, and Burien.

Seattle


Road construction photo of a workzone: Three workers visible amid construction cones in the new roadway. Crews completing concrete pours near the intersection of 26th Avenue SW and SW Roxbury Street

Crews completing concrete pours near the intersection of 26th Avenue SW and SW Roxbury Street

26th Avenue SW between SW Barton Street and SW Roxbury Street

  • Demolition, excavation, and grading
  • Installing curb and gutter, sidewalk, and ADA-compliant ramps
  • Electrical and utility work

Note: People driving will not be able to access 26th Avenue SW from SW Cambridge Street

15th Avenue SW and SW Roxbury Street

  • Demolition
  • Forming and pouring sidewalk
  • Electrical and utility work

Note: 15th Avenue SW will be closed to vehicular traffic south of SW Roxbury Street

26th Avenue SW and SW Roxbury Street

  • Demolishing bus zone foundation and panels

White Center

 

Road construction photo with a concrete truck and compactor

Grading along 15th Avenue SW

15th Avenue SW and SW 102nd Street

  • Electrical and utility work

15th Avenue SW and SW 107th Street

  • Installing sidewalks, driveways, curbs, gutters, and ADA-compliant ramps
  • Grading and pouring roadway

Ambaum Boulevard SW and SW 112th Street

  • Forming and pouring a bus zone foundation

Burien

Construction photo in Burien: Bus zone foundation installation along Ambaum Boulevard SW. Utility boxes amid gravel, sidewalk forms and construction cones, and a Businesses are Open A-board sign.

Bus zone foundation installation along Ambaum Boulevard SW

Ambaum Boulevard SW from SW 116th Street to SW 122nd Street

  • Installing a bus zone foundation
  • Grading and pouring sidewalks and curbs

Ambaum Boulevard SW and SW 128th Street

  • Installing curbs, gutters, and sidewalks
  • Electrical and utility work
  • Demolition, excavation, grading, and paving roadway
  • Forming and pouring a bus station foundation

Ambaum Boulevard SW and SW 142nd Street

  • Demolition, excavation, and grading roadway
  • Electrical and utility work

Ambaum Boulevard SW and SW 136th Street

  • Handrail installation

Questions during construction? Contact us!

We are committed to being a good neighbor. Thank you for your patience as we improve transit in your area. Keeping you informed and minimizing impacts are our top priorities. Throughout construction we will:

  • Be available for questions
  • Provide advance notice about construction through email updates, flyers, and other promotions
  • Maintain access to businesses and residences

RapidRide H Line Outreach Team