June 2025 update: Metro’s Fixed Assets State of Good Repair Program

Aerial photo of Metro bus bases in Seattle (2018)

June 2, 2025 updates: The State of Good Repair program A/E contract (KC001295) is in the final stages of selection with an award expected shortly.

The GC/CM contract (KC001248) is expected to advertise in late Q2 2025. The initial stages of the GC/CM contract are expected to focus on 10 currently funded priority projects shown below.
(State of Good Repair Initial Projects Summary Master Program Schedule May 18, 2025 PDF.)

Schedule chart of State of Good Repair Master ProgramMetro will be seeking a GC/CM to collaboratively work with Metro teams and stakeholders to develop cost effective solutions to deliver needed construction improvements while minimizing impact to ongoing operations at Metro facilities.

One of the GC/CM tasks will be to conduct industry outreach and develop a work packaging strategy that provides subcontracting opportunities consistent with King County goals. Another early activity will be to identify and implement strategies to procure high priority early work such as heavy duty bus lifts for the 1134246 TDC Atlantic Base Bus Lift Replacement project.

Please check the upcoming capital projects site for updated forecasts for this and other contract opportunities. The site may be found at this address:
https://kingcounty.gov/en/dept/executive-services/about-king-county/business-operations/finance-business-operations/procurement-payables/upcoming-projects

 

Metro’s plans for implementing the State of Good Repair (SGR) program continue to advance.

Metro held a combined virtual and in-person open house on Nov. 21, 2024 to update interested consultants, contractors and suppliers on upcoming SGR projects and planned procurements.

The meeting information included a briefing may be found here: (20241121 KCM_SGR_OpenHouse_Presentation Slides final)

Many participants signed the online and in-person registers providing their contact information including organization, capabilities, registrations and certifications. That information may be found here: KC001248-20241121-open-house-attendees

Fixed Assets State of Good Repair (SGR) Program overview

Metro is embarking on the next phases of a multi-year program to renew and replace vital infrastructure to maintain a high level of reliability, service and safety to its ridership and community. The program includes multiple transit maintenance bases and route facility improvements located across various Metro sites in King County. Funding is likely to include a mix of programmed King County local and grant funds.

Most of the program is currently envisioned to be delivered as bundles and packages of similar projects. Metro has recently updated project schedules based on changing services requirements and facility conditions. Preliminary project lists and schedules (subject to refinement) are described below.

Bundle 1 – General Infrastructure Improvements

Work will consist of packages of infrastructure improvements including site infrastructure, systems, facilities upgrades and equipment work primarily at operational maintenance bases. Initial project estimates for the projects are up to $160 million, subject to validation as planning and design advances.

Projects include underground storage tanks, underground utilities, routine and major equipment replacement, bus lifts, paving, building systems, fire systems, and in-route facilities such as comfort stations. Work will be coordinated with and support upcoming electrification work at several of the bases.

State of Good Repair timeline
(Package 1 timeline updated 2-5-2025)
State of Good Repair timeline
(Package 2-A timeline updated 2-5-2025)
State of Good Repair timeline
(Package 3-A and 3-C timeline updated 2-5-2025)

 

Timeline graphics for upcoming project bundles in the State of Good Repair program

State of Good Repair package 6 timeline
(Package 6 timeline updated 2-5-2025)

Bundle 1 Current Schedules

Bundle 1 Contracting opportunities

Metro anticipates hiring a design team for projects not yet in design and plans to begin selection this fall.

Metro plans to utilize Alternative Project Delivery methods to improve the speed and cost effectiveness of project delivery. Earlier this year, Metro obtained approval from the State of Washington Capital Projects Advisory Review Board’s Project Review Committee for Bundle 1 projects using General Contractor/Construction Manager (GC/CM) delivery. Under GC/CM delivery, the contractor team is hired during design to help with estimating, scheduling, constructability review and subcontracting. Construction is contracted in a second phase near the end of design through a combination of negotiated and competitive contract packages and subcontracts designed to optimize construction, supporting participation by a variety of small and disadvantaged contractors and suppliers.

Metro also plans to procure bus lifts for installation by the GC/CM team at multiple locations.

All three contracts are expected to begin selection in the near future.

 

Timeline of bundle 1 SGR infrastructure graphic
(SGR timeline updated 2-5-2025)

Bundle 1 Anticipated Procurements

Metro expects that much of the construction to be provided by the GC/CM will be procured under a variety of subcontracts. Metro expects to work collaboratively with the selected GC/CM team to identify subcontracting opportunities which would provide for greater opportunity for small and disadvantaged subcontractors and suppliers. Under the State PRC approval, the selected GC/CM (with Metro’s concurrence) will be allowed to select and negotiate subcontracts for Electrical, Mechanical, Civil Utilities, Underground Tank and Vehicle Lift work.

Bundle 2 – SGR Electrical & Trolley Infrastructure 

Bundle 2 consists of eight projects focused on electrical infrastructure refurbishment, primarily focused on sustaining and improving Metro’s trolley bus system. It is expected to include switchgear, medium voltage switches, and substation replacements. Initial project estimates for the eight projects are $58.6 million, subject to validation as planning and design advances.

This work is currently planned to be delivered through a Progressive Design-Build contract subject to approval by the State of Washington’s Capital Projects Advisory Review Board Project Review Committee. Under this method, a single design and construction team is hired early in the projects based primarily on qualifications to develop plans and costs meeting the owner’s requirements. This approach will allow Metro to work collaboratively with the selected team to identify significant consulting, supply and construction subcontracting opportunities which would be selected later.

Preliminary Bundle 2 schedules (subject to refinement) are presented below:

Bundle 2 timeline graphic for State of Good Repair program

Bundle 2 – Potential Progressive Design-Build Projects 

Bundle 2 SGR trolley anticipated timeline for State of Good Repair program

Bundle 2 Upcoming Contracts

Metro envisions holding one or more additional open house event(s) prior to submitting its PRC application. The program has been delayed a year from earlier plans and currently Metro plans to begin selecting a team during 2026. Metro anticipates selecting a team consisting of the prime contractor(s) and designer(s) in the initial selection and collaboratively selecting a large portion of remaining team members later to maximize opportunities for participation by a diverse array of firms.

Equity and Social Justice Goals

ESJ goals will be set as part of the Procurement Process. King County’s Master Community Workforce Agreement will apply to the construction of both bundles.

Past Outreach

Metro conducted open houses in November 2023 to introduce the projects. Additional information and materials provided during past Open House events can be found at the following links:

King County’s E-Procurement Supplier Portal 

Please be advised that the official advertisement for these projects will be published through King County’s E-Procurement system. To receive future notifications, please be sure your firm is registered in King County’s E-Procurement Supplier Portal.

Questions? 

Should you wish to obtain additional information about the Bundle 1 A/E, please contact Alice Phoenix (Contracting Specialist) at Alice.Phoenix@kingcounty.gov or 206-263-9311. For GC/CM questions contact Kelly McKeever  Kelly.McKeever@kingcounty.gov  206-263-9389.

For the Bundle 2 work please contact Brian Berard, the Fixed Assets State of Good Repair Project Manager at bberard@kingcounty.gov or 206-263-4160.

 

Leave a Reply