King County Metro, in partnership with the Seattle Department of Transportation (SDOT) and the City of Burien, is working to upgrade Metro Bus Route 120 — one of our 10 busiest routes — to the RapidRide H Line.
We will be sending email updates monthly to keep you informed on what to expect near you. We’ll also be reaching out to route neighbors, businesses, and local community organizations throughout construction to notify them when and where work will happen, as well as what impacts to expect.
Please feel free to share this information with your neighbors and encourage them to sign up for project email updates.
RapidRide H Line to launch in March 2023
The original timeline of the RapidRide H Line project has been extended by several months due to unforeseen construction and materials delays. RapidRide H Line will now launch in March 2023 rather than fall 2022. Read more about the updated project timeline and construction progress on our blog.
Work resuming at several locations
Concrete deliveries have resumed throughout the region and construction is continuing at the following locations:
- 15th Avenue SW and SW Roxbury Street
- 15th Avenue SW and SW 102nd Street
- 15th Avenue SW and SW 107th Street
- 26th Avenue SW and SW Roxbury Street
- Ambaum Boulevard SW and SW 112th Street
- Ambaum Boulevard SW, between SW 116th Street and SW 122nd Street
- Ambaum Boulevard SW and SW 128th Street
- Ambaum Boulevard SW and SW 136th Street
- Ambaum Boulevard SW and SW 142nd Street
Join us for our virtual construction office hours on May 26, 2022, from 5 p.m. to 6 p.m. on Zoom
We hope you’ll join us on Zoom to learn more about the project and ask questions! These are informal events; we welcome you to come and go as you please.
How to join the meeting:
- To join online: Launch Zoom meeting (Meeting ID: 867 4154 5962)
- To join by phone: 1-253-215-8782 (Find your local number here)
- To request interpretation services for these virtual events, please contact us before the meeting via phone, at 206-257-3079, or email us at rapidride@kingcounty.gov
Businesses are open during construction
With construction ongoing throughout the project area, Metro is reminding the public that businesses throughout the project area remain open. Visit our Metro Matters blog to learn more about Metro’s ongoing work in the Seattle, White Center and Burien communities.
- Businesses are open during construction (English)
- Los comercios estarán abiertos durante la construcción. (Spanish)
- 공사 중 정상 영업합니다. (Korean)
- Ganacsiyada ayaa furnaan doona inta dhismuhu socdo. (Somali)
- Các doanh nghiệp mở cửa trong khi xây dựng. (Vietnamese)
- 施工期間企業/商戶正常營業。(Chinese traditional)
- 施工期间企业/商户正常营业。(Chinese simplified)
What’s happening now?
What to expect during construction
Construction on the RapidRide H Line project began in June 2021 and is expected to last through March 2023. Typical work hours are Monday through Friday, 7 a.m. to 3:30 p.m., with some nighttime and weekend work.
During construction, you can expect:
- Noise, vibrations, and dust in the project area
- Temporary parking restrictions
- Periodic lane and driveway closures
- Large machinery and truck activity
- Construction staging and parking impacts near the construction site
- Some sidewalk, intersection, and lane closures
- Detours for people walking, biking, and rolling
- Temporary bus detours and bus stop relocations for Route 120 and other area transit and bus routes.
- Flaggers to direct traffic around work areas
Crews are installing safety improvements and bus station upgrades along the route. Work has already started or will begin in the coming weeks at the following locations in Seattle, White Center, and Burien.
Seattle
26th Avenue SW and SW Cambridge Street
- Demolishing, excavating, and grading roadway
- Installing curb and gutter, sidewalk, and ADA-compliant ramps
15th Avenue SW and SW Roxbury Street
- Electrical and utility work
- Traffic signal modifications
Note: 15th Avenue SW will be closed to vehicular traffic south of SW Roxbury Street
26th Avenue SW and SW Roxbury Street
- Electrical and utility work
White Center
15th Avenue SW and SW Roxbury Street
- Electrical and utility work
- Forming and pouring bus station foundation
26th Avenue SW and SW Roxbury Street
- Forming and pouring bus station foundation
15th Avenue SW and SW 107th Street
- Forming and pouring bus station foundation
- Installing curb and gutter, sidewalk, and ADA-compliant ramps
- Forming and pouring median island
Ambaum Boulevard SW and SW 112th Street
- Grading, forming, and pouring sidewalk
- Installing curb and gutter and ADA-compliant ramps
- Forming and pouring bus zone foundation
Burien
Ambaum Boulevard SW from SW 116th Street to SW 122nd Street
- Grading, forming, and pouring sidewalk
- Installing curb and gutter
- Forming and pouring bus zone foundation
Ambaum Boulevard SW and SW 128th Street
- Electrical and utility work
- Demolishing, excavating, and grading roadway
- Installing curb and gutter, sidewalk, and ADA-compliant ramps
- Build retaining wall
Ambaum Boulevard SW and SW 136th Street
- Electrical and utility work
- Forming and pouring bus zone foundation
Ambaum Boulevard SW and SW 142nd Street
- Grading, forming, and pouring sidewalk
- Forming and pouring bus zone foundation
Ambaum Boulevard SW and SW 148th Street
- Electrical and utility work
Ambaum Boulevard SW and SW 150th Street
- Electrical and utility work
Do you have questions about construction? Contact us!
Thank you for your patience as we improve transit in your area. Keeping you informed and minimizing impacts are our top priorities. Throughout construction we will:
- Be available for questions
- Provide advance notice about construction through email updates, flyers, and other promotions
- Maintain access to businesses and residences
RapidRide H Line Outreach Team
- Construction hotline: 206-257-3079
- Email: rapidride@kingcounty.gov
- Webpage: kingcounty.gov/metro/hlineinfo
Sign up for RapidRide H Line email or text alerts to stay up to date on construction schedule and impacts.