King County Metro is providing information and soliciting feedback from contractors interested in a design-bid-build project to upgrade electrical equipment at the Broad Street Substation. This substation, located at 319 Sixth Ave. N. near Seattle Center, provides power to 14 Metro trolley bus lines throughout North, Central and South Seattle.
Metro is currently designing a replacement of the Broad Street Substation AC breakers, transformers and rectifiers. The existing DC breakers will remain in place. Each rectifier and transformer will need to be replaced individually while the other remains in service. Design currently stands at 90%, with construction anticipated to start approximately Q1 2023.
Please see the Technical Scope of Work for more detailed information.
Reference documents (PDFs)
- Preliminary Site Plan
- 2022_05May_31 – Broad St 90percent Plans
- Technical Scope of Work
- NEW! (added June 30, 2022) Broad Street Open House Presentation
Virtual Open Houses
- Tuesday, June 21, 9am-10am (Pacific Standard Time)
- Wednesday, June 22, 10am-11am (Pacific Standard Time)
- Monday, June 27, 9am-10am (Pacific Standard Time)
- Tuesday, June 28, 9am-10am (Pacific Standard Time)
Contact information
Randy Poplock, King County Metro Capital Project Manager, randy.poplock@kingcounty.gov.
King County Metro – Broad Street Substation Equipment Replacement Project
Purpose
To provide virtual open-house meetings (more detail below), and solicit feedback from contractors interested in the upcoming replacement of two existing rectifiers and transformers located in the Broad Street Substation in downtown Seattle.
Project Background
Metro is currently at 90% design for replacement of the Broad Street Substation equipment, including AC breakers, transformers and rectifiers. The existing DC breakers will remain in place. Each rectifier and transformer will need to be replaced individually while the other remains in service. Construction is anticipated to start approximately Q1 2023.
Funding
This project will have federal (Federal Transit Administration) funding, and is thus subject to FTA requirements, and will be fully funded through the construction, commissioning/startup, and closeout phases.
Budget
The total construction contract value of the project is estimated to be in the range of $4.5 million to $5.5 million.
Project Delivery
Design-bid-build, lump sum.
Schedule Assumptions
The tentative schedule is:
- Advertise:
Q3 2022Q1 2023Q3 2023 (date updated Feb. 17, 2023). The project will be advertised through King County’s Procurement website. Visit the web page to register and view solicitations. - Notice to Proceed (NTP):
Q1 2023Q4 2023 (date updated Feb. 17, 2023). - Substantial Completion: NTP + 20-24 months
Scope of Work
Electrical Scope
This scope includes removal of existing equipment, procurement and installation of replacement DC traction power equipment, 125VDC equipment, Remote I/O, updating existing SCADA system, cabling and miscellaneous electrical hardware as well as testing, commissioning, startup and training. It includes two (2) 1.5MW, 26.4 kV to 672 Vdc power conversion systems into the existing Broad Street traction power substation. Each power conversion system, which includes a primary AC circuit breaker, transformer, rectifier, protective relaying, remote I/O will be installed under staged construction whereby one AC to DC rectifier is on-line and continuously feeding the existing trolley system via the existing Broad Street DC feeder breakers.
Please see attached Technical Scope of Work for more detail.
Structural Scope
Structural upgrades, using Fiber Reinforced Polymer (FRP), will be required for the building’s slabs, beams, and columns to accommodate the heavier weight of the new equipment. Some demolition will be required along with need for dust control and regulated material mitigation.
Other Factors
To maintain continuous service, the project construction must be performed in two distinct phases (remove and replace one rectifier at a time without interrupting the other).
Seattle City Light will be performing the Broad Street Substation Inductor Project simultaneously, with construction expected to occur between approximately July 2023 to February 2024.